A portal is ready when it captures the intended movement, rejects nearby noise and sends only validated events to the system of record. Define the acceptance boundary before go-live testing.
01 / SAHA NOTU
Define the valid movement
Write the lane, direction, item or load unit, trigger, timing and system action that together make a movement valid. A reader detecting a tag is not enough to approve the business event.
02 / SAHA NOTU
Test negative cases
Include staged goods, adjacent lanes, parked assets, reverse movement, overlapping readers, duplicate reads and interrupted passes. These cases reveal whether nearby visibility becomes an unintended inventory event.
03 / SAHA NOTU
Isolate adjacent activity
Describe the nearby items, lanes, readers and traffic that must not be counted as part of the accepted movement. Test boundary crossings and overlapping activity separately from the normal pass.
04 / SAHA NOTU
Agree the evidence
Record intended-movement coverage, false and duplicate event checks, event-to-system handoff, exception ownership and recovery action. Set project-specific thresholds before testing instead of borrowing a generic percentage.
05 / SAHA NOTU
Test recovery and change
Exercise missed reads, offline devices, delayed responses, partial passes and a changed item mix. Record the operator action and final system state, then define which changes require a new acceptance run.
06 / SAHA NOTU
Freeze the working baseline
Keep tag placement, physical layout, antenna position, reader settings, trigger logic, software rules, test samples and sign-off together. Retest after the site, item mix or workflow changes.